   Scheduling of Unrelated Parallel Machines using Two Multi Objective Genetic Algorithms with Sequence-Dependent Setup Times and Precedent Constraints  
   
نویسنده Safaei S. ,Naderi R. ,Sohrabi A. ,Hatami A.
منبع international journal of advanced design and manufacturing technology - 2015 - دوره : 8 - شماره : 4 - صفحه:63 -74
چکیده    Abstract: this paper considers the problem of scheduling n jobs on m unrelated parallel machines with sequence-dependent setup times. to better comply with industrial situations, jobs have varying due dates and ready times and there are some precedence relations between them. furthermore sequence-dependent setup times and anticipatory setups are included in the proposed model. our objective is to determine a schedule that minimizes makespan and number of tardy jobs. the problem is np-hard, so for obtaining an optimal solution, in reasonable computational time, we propose two multi objective genetic algorithms (moga). to evaluate the proposed algorithms, random test problems are produced in medium and large sizes with tight due dates. after setting the parameters, the performances of these algorithms are evaluated using the concept of data envelopment analysis (dea), distance method, and a number of non-dominated solutions.
کلیدواژه Data Envelopment Analysis ,Genetic Algorithm ,Makespan ,Multi-Objective ,Number of Tardy Job ,Parallel Machine Scheduling ,Precedence Constraints ,Sequence-Dependent Setup Times ,Topsis Method
آدرس shahid beheshti university, Department of Industrial Management, ایران, semnan university, Department of Industrial Management, ایران, Ministry of Health and Medical Education, Research Center of Health Reference Laboratory, Department of Molecular Biology, ایران, university of tehran, Farabi College, Department of Business Management, ایران