   techno-economic feasibility study of the gunde teklehaymanote micro-hydropower plant at tindwat river, central gondar, ethiopia  
   
نویسنده belay a. k. ,atenafu d. ,birhan s. ,tegengn t.
منبع iranica journal of energy and environment - 2020 - دوره : 11 - شماره : 2 - صفحه:130 -136
چکیده    Ethiopia has a high potential for water for hydro-power development. even though there is untapped potential, the country's electricity coverage is poor. this paper presents a technical-economic feasibility study of gunde micro hydropower at the tindwat river, central gondar, ethiopia. in the techno-economics study, the analysis was made for energy modeling, economic scenarios, and sensitivity, risk, and emission analyses. the study shows that this mini-hydropower project can be developed with an installed power of 18 kw, where the kaplan turbine is recommended. the construction of small scale hydropower in the tindwat river is technically and economically feasible with total net present cost of us $ 253537, cost of energy $0.09/kwh, simple payback period of 5.9 years, and internal rate of return 23.9%. the result also shows that construction of hydropower curtails greenhouse gas emissions of carbon dioxide by 588.65m^3 of gasoil per year. it also showed that small hydroelectric power generation from tindwat river would improve the electricity supply to gunde teklehaymanote monstery and off-grid rural communities.
کلیدواژه prefeasibility analysis ,small hydro power ,tindwat river ,turbines
آدرس university of gondar, institute of technology, mechanical engineering department, ethiopia, university of gondar, institute of technology, hydraulics engineering department, ethiopia, university of gondar, institute of technology, electrical and computer engineering department, ethiopia, university of gondar, institute of technology, mechanical engineering department, ethiopia
 
     
   
Authors
  
 
 

Copyright 2023
Islamic World Science Citation Center
All Rights Reserved